|
Redland Brick Harmar Plant
Creating a new, energy-efficient, three-building facility to manufacture and process clay bricks created a variety of challenges. All were handled
so this 227,000-square-foot, $8.5 million project was not only done in compliance with Act 222, but also finished ahead of schedule and within
the owner's budget. Preparing a "green field" by cutting and filling 87,000 cubic yards was necessary to reduce settlement differential in the
manufacturing/kiln building. Language barriers and measurement conversions were addressed, so that European contractors for the French kiln and
German gring equipment delivered materials properly. Contractors and union craftsmen employed value-engineering strategies to save the owner more
than $100,000 by recommending items such as battered wall designs instead of step walls. And, time was saved by ordering a pre-engineered building
with a temporary column to allow for steel erection to begin, while sheltering workers so that they could work during the winter.
|
FirstEnergy Rapid Discharge Rail Unloader
Capturing significant savings was critical for the nation's fourth largest investor-owned electric system - but it could only happen if an aggressive
project schedule was completed on time. Teamwork among designers, management, contractors and union craftsmen made it happen, and a state-of-the-art
rapid discharge rail unloader was constructed on time and with expert results. Now, FirstEnergy's Bruce Mansfield power plant in Shippingport, PA.,
processes the fuel to generate electricity in a cost-effective manner for its customers.
|